Commercial Draw Inspections: Order Forms, Vendor Contracts and SLAs

Avatar photo
Scott Thissen
Nov 17, 2026
Illustration of a central banking icon connected to insurance, contract, analytics, and reporting icons, representing an integrated construction lending and financial management platform.

Commercial construction lenders manage draw inspection vendors and service-level agreements (SLAs) with three controls that cover the work before and after the site visit. A standardized order form with required fields gives every inspector the full scope and keeps incomplete orders from going out.

A per-deal contract tied to a budget line requires a written explanation for any overage and invoices in one standard format. An SLA measures turnaround and report completeness together.

Why Inspections Slow Commercial Draws

Commercial inspections slow draws because each deal brings more scope, more parties, and its own requirements. A draw inspection is an independent site check of billed work before funds go out, and the construction draw inspection basics cover what one includes.

A commercial project can add a construction consultant, a general contractor (GC), many subcontractors, and custom requirements such as stored-materials review. Each added party is one more handoff where an order can stall.

In our experience, the site visit is rarely the bottleneck. The days go to ordering, vendor follow-up, and invoicing, before and after the inspector is on site.

Picture a loan administration team with a commercial draw waiting on an inspection. The order lacked the stored-materials location the inspector needed, so the inspector emailed back and waited.

The deal’s inspection contract also expired at the original completion date, with the project four months behind. Nobody owned vendor follow-up, so the delay surfaced when the GC called the lender to ask where the money is.

What a Commercial Inspection Order Form Should Capture

A commercial inspection order form should capture every field the inspector needs, with critical fields required so incomplete orders can’t be submitted.

Start from a template library, then customize the form per deal. A ground-up multifamily loan and a tenant-improvement loan need different fields.

Structured fields also become portfolio data. When estimated percent complete is a number on every order, credit teams can report it across all active loans.

A commercial order form should capture the following:

  • Site access contact: Name, phone, and access hours for the person who can open the site.
  • Draw amount by line item: The requested amount for each budget line, so the inspector checks the billed work.
  • Approved budget and change orders: The current schedule of values, including every approved change order.
  • Estimated percent complete: The GC’s estimate, recorded as a number for comparison with the inspector’s finding.
  • Stored materials: Location and billed value of materials stored on site or off site.
  • Report format and due date: The deliverable the lender expects and the date it’s due.
Required fields on a commercial draw inspection order form.

Office of the Comptroller of the Currency (OCC) supervisory guidance for OCC-supervised banks sets the bar for the report. The OCC Comptroller’s Handbook on Commercial Real Estate Lending asks if inspection reports are “sufficiently detailed to support disbursements.”

The handbook also looks for inspections “performed by a party not reporting to the loan origination function.” A complete order gives that independent inspector what the report needs.

How to Tie Inspection Contracts to the Budget

Tie each inspection contract to one deal and one budget line, so inspection costs are tracked like any other project cost.

A per-deal contract records the fee, scope, visit frequency, and end date. Mapping it to a budget line, such as inspection fees in soft costs, keeps the remaining balance visible.

Require a written explanation for any invoice above the contract amount. A re-inspection or schedule extension can justify more cost, and the reason belongs in the file before payment.

Ask vendors to invoice in one standard format with the loan number, draw number, visit date, and contract reference. Staff can then match each invoice to its order without opening the PDF.

Per-deal contracts can sound like extra admin. With a template, a new contract needs the fee, budget line, and end date, and the rest carries over.

How to Manage Inspection Vendors and SLAs

Inspection vendors are third parties in the eyes of an examiner, so manage them like any other third party. The OCC Handbook names inspectors and engineers as common commercial real estate (CRE) third-party relationships. It says they “should be incorporated into the bank’s third-party risk management processes.”

In September 2026, the OCC, the Federal Reserve, the FDIC, and the National Credit Union Administration (NCUA) published proposed third-party risk management guidance. It would replace existing third-party guidance and says “a service level agreement can define performance measures.” It’s a proposal, and the agencies extended the comment period to December 16, 2026.

Pair every speed measure with an accuracy measure. An SLA that rewards turnaround alone pushes inspectors toward thin reports, which send draws back for a second visit. Track completeness, meaning every billed line addressed and percent complete recorded, next to days from order to report.

Bring Your Own Inspector vs a Prenegotiated Network

Your own inspectors keep trusted relationships and your rates, and your team carries contracting, insurance checks, and backup coverage. A prenegotiated network brings set rates, delivery SLAs, confirmed insurance, and reassignment when a vendor can’t complete an order.

FactorYour Own InspectorsPrenegotiated Network
RatesNegotiated by the lenderPrenegotiated
Turnaround termsSet in each contractDelivery SLAs in place
InsuranceChecked by the lenderConfirmed by the network
Vendor can’t completeLender finds a replacementOrder is reassigned

The models can coexist, with trusted inspectors in core markets and a network for new geographies. Contract and SLA terms matter more than the sourcing model.

Best Practices for Inspection SLAs

Four practices keep inspection SLAs useful:

  • Set contract end dates past expected completion: Projects run late, and an expired contract stops ordering on a live loan.
  • Talk to the vendor before making a field required: A required field the inspector can’t fill on site blocks every order.
  • Measure from order to accepted report: Stop the clock when the report passes review, so rework counts against the SLA.
  • Review results by vendor each quarter: Compare turnaround and completeness, then shift volume or renegotiate terms.

Required fields move effort to ordering, when the person placing the order already has the answers.

What Inspection Management Looks Like Across a Portfolio

Across a portfolio, inspection management turns into a data problem. A small team carries many loans, each with a recurring inspection to order, follow up, and pay.

For credit leadership, the risk is stale or inconsistent data. If one vendor reports percent complete as a number and another buries it in narrative, nobody can compare completion to funding across the book.

That gap feeds construction finance risk, because a loan funded ahead of completion is exposed if the project stalls. Consistent fields also support how lenders review a construction draw request on every draw.

How Built Manages Commercial Draw Inspections

Built is the AI operating system for real estate finance, serving 300+ lender clients across the full lifecycle, from pipeline management and deal screening to portfolio management. Its draw inspections workflow creates inspection orders from draws and uses inspection data to validate each draw against verified progress. Orders start from the draw and inspection data flows back into it.

Lenders can keep their own inspectors on a lender-managed list or select from Built’s CRE inspection network by geography and price. Network inspectors are pre-vetted, with at least three years of experience, verified insurance, and background checks, and Built handles invoicing, payments, and inspector support for those orders.

Vendors can assign and reassign orders, and inspectors can recommend funding amounts at the line-item level (Winter 2025 release details). Time-based order scheduling places recurring orders on a set schedule. Inspector-recommended amounts give the loan administrator a line-item funding figure to compare against each draw request, and AI-generated summaries of inspection orders put project status, budget progress, and key dates in one view.

In the past 12 months, 368 inspection firms filled orders on Built. Through the Built Marketplace, Built delivers 30% faster inspection completion at the median, and two-thirds of inspections are completed within three days. Lenders can order from Built’s inspection network without leaving the draw.

To see inspection orders, vendors, and recommended funding amounts in one draw workflow, Book a Demo.

Commercial Draw Inspection FAQs

How Should Commercial Construction Lenders Manage Draw Inspection Vendors and SLAs?

Lenders manage commercial draw inspection vendors with a required-field order form, a per-deal contract tied to a budget line, and an SLA. The contract should require written explanations for overages and invoices in a standard format. The SLA should measure turnaround and report completeness together.

What Is the Difference Between a Residential and a Commercial Draw Inspection?

The biggest difference is how progress is measured. Residential draw inspections usually use percent of completion, where the inspector reports what percent of each budget line is complete. Commercial projects, with larger budgets and more complex scope, are better suited to value-based inspections, where the inspector validates the dollar amounts requested in the draw. Value-based inspections need elevated inspector access to hard costs, and the method should stay the same for the life of the project.

Can I Use My Own Inspector?

Yes, lenders can keep their own inspectors at their own rates and still run every commercial draw inspection through a standard order form, contract, and SLA. Your team then handles insurance checks, contract renewals, and backup coverage when the inspector is unavailable. A prenegotiated network can fill gaps in new geographies or absorb overflow.

What Happens If the Inspection Fee or the Inspector Changes Mid-Project?

Treat a fee change as a contract change, with the new fee and the reason recorded in writing and the budget line updated. If the inspector changes, reassign open orders and carry over the order form, contract terms, and prior reports so the new vendor starts with full context. Confirm the new vendor’s insurance before the next site visit.

Can I Set Up Recurring Inspections?

Yes, lenders can schedule recurring inspection orders on a fixed cadence, such as monthly, to match the draw cycle. Set the contract end date past expected completion so recurring orders don’t stop on a project that runs late. Review the recurring order when a major change order shifts the scope, and update the required fields to match.

Written by Scott Thissen

Scott Thissen is VP of Enterprise Sales at Built Technologies, where he leads go-to-market strategy and partnerships with top-tier financial institutions modernizing their construction and real estate lending operations.

Scott brings a unique perspective to lending technology: he combines deep sales leadership experience with hands-on expertise in how AI is reshaping customer conversations and deal dynamics. He’s spent the past year reimagining how sales teams can authentically engage with lenders on AI-driven transformation; moving beyond vendor pitches to genuine problem-solving around operational efficiency, risk, and scalability.

His work at Built focuses on helping his teams be consultative real estate experts for their clients navigating our new technology landscape, while building solutions that actually solve real lending problems. He’s passionate about creating frameworks that enable teams to sell smarter and build deeper customer relationships in an AI-driven world.

Scott lives in Brentwood, Tennessee, with his wife and three kids, and spends his free time running to kids soccer games and ballet recitals.